Mechanical
systems design and construction phase services for HVAC, plumbing, and fire
protection systems for new 2½ floor, 108,000 square foot Network Information
Center.
Mechanical
Contractor B&W Mechanical
Prime Consultant Howell Rusk Dodson
Construction Cost
$18,000,000 (total)
$2,850,000 (mechanical)
Central plant supplied
chilled water to downflow computer room air handling units with supply
plenum below raised floor.
Two 10,000-gallon underground
water storage tanks are used for emergency condenser water make-up to
cooling towers and can be filled with either domestic water or well
water.
The entire building can be
powered by emergency generators that are supplied by two 10,000-gallon
underground fuel tanks.
Central plant designed to accommodate future doubling of capacity
without interrupting cooling.