Multiple construction phases
of the project to accommodate continuous availability of required
minimum number of Operating Rooms.
-
Accelerated design and
construction schedule (six months total) to complete construction prior
to start of cooling season.
-
Revised design-basis
operating room conditions of 60°F at coincident 55% relative humidity
along with meeting requirements for simultaneous increase in outside air
intake quantity.
-
Two new 8700 CFM air-handling
units with secondary chilled water/glycol cooling coil providing 43°F
supply air.
-
Dedicated secondary-cooling,
air-cooled chiller with water/glycol circulating fluid supplying 37°F
chilled water to coils.
-
Overhaul of the existing
air-handling unit to address outside air intake, air mixing and
controls-related issues, and reconfiguration of the unit to serve
Surgery Suite less the operating rooms.
-
Renovation of ductwork system
in separate sub-phases to convert air terminals and steam humidifiers to
association with new air units.
-
Relocation of existing HVAC
equipment serving Central Supply and ETO Sterilizer to accommodate new
HVAC systems.