Chiller Plant
Scope
Construct a new chiller plant to serve current and future needs of Hospital System.
Owner Rockdale Hospital
Mechanical Contractor Batchelor & Kimball
Prime Consultant Tippett Clepper Architects
Construction Cost $1,600,000 (total) $890,000 (mechanical)
Special Circumstances
Construction phased to allow near-continuous plant operation.
New 750-ton capacity chiller and associated cooling tower.
New DDC System.
Provisions for future expansions of the hospital.
Reconfigured primary/secondary chilled water-piping system.
Extensive equipment relocation/replacement and project phasing.