Energy Plant, Chiller, and Tank

Scope

Phase I:   9,300-sq. ft. expansion to existing boiler/chiller plant.

Phase II:  Addition of second 800-ton chiller, cooling tower, and related pumps to first phase

                  expansion.

cooling towers and condenser water piping

Owner
Promina Cobb Hospital

Mechanical Contractor
Custom Mechanical

Prime Consultant
CDH Partners

Construction Cost
$2,700,000
 

Special Circumstances

        Phase I:

  • Construction phased to allow continuous plant operation.

  • New 800-ton chiller, cooling tower and related pumps.

  • Modified existing chilled water system to convert to primary-secondary pumping with variable secondary flow via variable speed drive or secondary pump.

  • Expansion of direct digital control system to serve Energy Plant expansion areas.

  • Installation of 15,000-gallon, underground fuel tank and piping system to serve new emergency diesel generator.

  • Expanded natural gas, water drainage and ventilation systems to serve 1,000-lb./hr. medical waste incinerator.

        Phase II:

  • Additional new 800-ton chiller, cooling tower and related pumps.

chiller and piping