Energy
Plant, Chiller, and Tank
Scope
Phase I: 9,300-sq. ft. expansion to
existing boiler/chiller plant.
Phase II: Addition of second 800-ton
chiller, cooling tower, and related pumps to first phase
expansion. |
 |
Owner
Promina Cobb Hospital
Mechanical
Contractor
Custom Mechanical
Prime Consultant
CDH Partners
Construction Cost
$2,700,000
|
|
Special Circumstances
Phase I:
-
Construction phased to allow
continuous plant operation.
-
New 800-ton chiller, cooling tower
and related pumps.
-
Modified existing chilled water
system to convert to primary-secondary pumping with variable secondary
flow via variable speed drive or secondary pump.
-
Expansion of direct digital control
system to serve Energy Plant expansion areas.
-
Installation of 15,000-gallon,
underground fuel tank and piping system to serve new emergency diesel
generator.
-
Expanded natural gas, water drainage
and ventilation systems to serve 1,000-lb./hr. medical waste
incinerator.
Phase II:
|
 |
|