Addition
and Renovation
Scope
Mechanical design and construction phase services
for the renovation of the existing 80-year-old Grady High School Campus.
Approximately 120,000 sq. ft. of the five-building campus was renovated
while more than 100,000 sq. ft. of new building was added.
The buildings included classrooms, a 25,000 sq. ft. gym with locker
rooms, a 500-seat theater, a 700-seat cafeteria with associated kitchen, a
music building (band, choral and orchestra rooms) with recording capability,
and a TV studio. |
|
 |
Owner
Atlanta Public Schools
Mechanical Contractor
Ragan Enterprises, Inc.
Prime Consultant
Perkins and Will
Construction Cost
$24,000,000 (total)
$4,000,000 (mechanical) |
|
Special Circumstances
-
All
classrooms are served by energy efficient water-source heat pumps.
-
All
buildings are equipped with energy recovery ventilators to lower utility
costs and HVAC loads.
-
High efficiency (90%+) boilers are utilized for building heating.
-
Acoustically designed Band, Choral, Orchestra Rooms, and Television
Broadcast Studio.
-
New
campus distribution piping systems for natural gas, domestic water, and
fire protection water.
-
Acid resistant piping system and central acid dilution tank serving the
eight science classrooms.
-
All
buildings protected by new fire sprinkler systems.
- Design included phasing
requirements necessary to allow school to remain in operation during
construction.
|
|
|
|