Art &
Humanities Building and Kell Hall Renovations
Scope
Revise entire concept of chilled water supply to the building and replace worn
out high-pressure steam boilers with new steam plant to serve Kell Hall.
Owner
Georgia State University
Contractor
Peachtree Mechanical
PrimeConsultant
Johnson, Spellman & Associates
ConstructionCost
$401,000
Special Circumstances
Work completed during occupancy of animal care laboratory.
New
100BHp 100 psig operating pressure fire-tube boilers and deaerator tank
installed.
Direct digital control of boiler operation via campus control system.
Existing chillers removed, new piping mains extended from central plant,
and new building chilled water secondary pumps installed.
Fast track design. Entire
design, bid, and construction in less than 180 days.