Renovate the existing HVAC systems of the
North Wing of Building #3 and incorporate a new Battery Lab into the design.
Owner Georgia Tech Research
Institute
Mechanical Contractor CAE Diversified Services
Prime Consultant Johnson, Spellman & Associates
Construction Cost $700,000
Special Circumstances
New variable air volume 22,000 CFM
roof mounted, custom air handling unit with pre-heat coil, cooling coil,
steam humidifier, and variable speed relief and supply air fans.
Terminal units with hot water reheat
capacity.
Hydrogen and carbon monoxide
monitoring of the Battery Lab.
Differential pressure requirements
between laboratory and supporting spaces.
Acid resistant waste and vent,
natural gas, compressed air serving fixtures in Battery Lab.
Compressed air regulated to two (2) different pressures.
Type III water system supplying
fixtures in Battery Lab and a Type I point of use water system.
Strict environmental requirements
(temperature, humidity and noise ranges) for various laboratory spaces.