Complete mechanical systems design and
construction phase services for HVAC, plumbing, and fire protection systems to
serve New Emory School of Public Health and renovation of the Michael Street
Central Plant.
Owner
Emory University
Mechanical Contractor
Paul W. Heard & Co.
Prime Consultant
Lord, Aeck & Sargent
Construction Cost
$12,000,000
Special Circumstances
Full research lab on first floor.
High-rise building systems.
New 1,000-ton chiller and associated
ceramic cooling tower.
New outdoor underground chilled
water and hot water distribution piping were routed from the central
plant to the new building.
Total central plant tonnage of 3,800
tons with space for additional chillers and cooling towers.
A new plate and frame heat exchanger
was added providing the central plant with waterside economizer.
Central plant controls were
completely replaced with a campus integrated system.