Complete mechanical design and construction phase
services for construction of new 35,000 square foot gymnasium building with
seating for 2,700 occupants and the addition of a new 30,000 square foot
Performing Arts building with 700-seat auditorium, including new Chorus and
Band rooms.
Owner
Atlanta Public Schools
Mechanical Contractor
Tebarco Mechanical
Prime Consultant
Richard + Wittschiebe
Construction Cost
$8,900,000 (total)
$1,288,000 (mechanical)
Special Circumstances
Incorporated semi-custom HVAC
rooftop equipment with integral heat recovery wheels and modulating hot
gas reheat for humidity control.
Zoned Gymnasium air systems to
maximize energy savings during partial occupancy.
Utilized Demand Control Ventilation
(DCV) strategy for all high-density spaces.
Designed Auditorium air system to
minimize acoustical noise levels.
Used energy-efficient VAV system
with parallel induction units (PIUs) for band
and chorus suites.