Complete replacement of existing Hot Water and Chilled Water Central Plant and
associated ancillary pumps located in satellite mechanical rooms, serving
250,000 square feet of occupied space in seven buildings of a college campus.Five new hot water heating boilers of 5 MMBTUH capacity and two new chillers of 1500 ton
capacity included in the scope of the project along with new primary,
secondary and tertiary pumps.
Owner
Board of Regents
Mechanical Contractor
Mann Mechanical
Prime Consultant
Johnson, Spellman & Associates
Construction Cost
$4,320,000 (total)
$3,110,000 (mechanical)
Special Circumstances
Fast-track project schedule under
"Construction Manager At-Risk" contract with nine-month timeline from
start of project to start-up of new Chilled Water Plant.
Multiple phases and sub-phases for
the demolition and new construction to meet the critical schedule for
start-up of new systems.
Critical interface of existing
building systems with new central plant that have a wide diversity in
heating and cooling demands.
Increased the cooling and
heating capacity of the Central Plant without increasing the physical
size of the Plant building while addressing the User's needs for
maximized accessibility to equipment.