New Parasitic Diseases Laboratory

Scope

Design the mechanical systems (HVAC, fire protection, and fuel storage) for a new 27,384 sq. ft. laboratory and support space.

Owner 
Centers for Disease Control

Mechanical Contractor
Meridian Contracting

Prime Consultant
Tippett Clepper & Associates

Construction Cost
$6,200,000 (total)
$1.650,000 (mechanical)


Special Circumstances

  • Phasing of the project into two separate construction periods to accommodate existing personnel.

  • Two custom 20,000 CFM, variable volume air handling units.

  • An above ceiling service corridor required all equipment requiring service (i.e., air valves, HVAC and plumbing control valves, etc.) to be within reach of the corridor.

  • Steam-to-hot water heat exchanger utilizing campus steam.

  • 120-gallon steam water heater utilizing campus steam.

  • Acid resistant waste and vent system.

  • A 12,000-gallon underground storage tank provides fuel to a 250kW stand-by generator.

  • Integration of the building automation system with HVAC equipment, owner equipment, and the building lighting.