Switching Facility Conversion

Scope

Fast-track project to convert an existing 40,000 sq. ft. warehouse into a tele-communication switching facility.

Mechanical Contractor
Mechanical Contractors Inc.

Prime Consultant
H.E. Hennigh

Construction Cost
$6,000,000 (mechanical)

Special Circumstances

  • Fully redundant mechanical system with a pair of 100-ton air-cooled chillers and associated pumps.

  • Two 100-ton variable speed modular air handlers with high efficiency filters, humidifiers, and 100% air-side economizers.

  • Provisions for future addition of third 100-ton chiller, pump, and air handler.

  • 6,000-gallon aboveground fuel storage tank serving the standby generator.

  • ADA compliant men’s and women’s toilets and shower.

  • Computerized direct digital control system utilizing a web-based user interface to allow remote access via the Owner’s intranet web browser.