Mechanical
systems design and construction phase services for replacement of
three 700-ton cooling towers.
Mechanical
Contractor
W.B. Wallis
Prime Consultant Guerra Stoll Barker
Construction Cost
$525,000 (total)
$300,000 (mechanical)
Special Circumstances
Project undertaken during the
spring to allow the three remaining towers to maintain 24-7
cooling while these three other towers were replaced.
New towers included stainless
steel basins, VSD’s, inverter duty motors, separate
motorized tower isolation valves, and full access to the top
deck for maintenance.
The construction schedule and
project cost were reduced by closely coordinating the tower
supply and return connections with the existing structural
supports to eliminate any modifications to the steel.